Programme of Piling Works at the Learning and Teaching Hub Site
Published: 17 November 2017
A programme of works on the Learning and Teaching Hub site over the next three months has started.
A programme of works on the Learning and Teaching Hub site over the next three months has started.
- From now – November 19: our main contractor, Multiplex, is carrying out earthmoving work to form a piling mat;
- November 20 – December 20: piling works along University Gardens;
- January 2018 - Earthworks to form capping layer;
- February – March 2018: main piling works.
Professor Frank Coton, Vice Principal (Academic and Educational Attainment) and Convener of the Learning and Teaching Hub Project Development Board, said: “I apologise in advance for any inconvenience that may be caused but I would add that we are now entering a prolonged period of construction on the site and we will have to work collaboratively to support the student experience while the new building is in construction. I am grateful for your support with this important project for the University.”
First published: 17 November 2017