Workstream 3 (W3): Rapid Deployment
This workstream will focus on those buildings that only require a wireless service upgrade / expansion as well as replace any near or end-of-life data network switches, rather than a total data network upgrade.
This allows for a rapid deployment across the campus where it's expected that we will only be in each of these buildings for a few weeks at a time as opposed to months which Workstream 4 (W4) will accommodate. As part of this workstream, all wireless access points (WAPs) will get the latest in data cabling to support them as well as have their network cabinets replaced where the existing ones can not accommodate the upgrade.
Buildings in Progress
Please note - Here you'll find the buildings currently planned for delivery through to March 2026. This information is contingent upon, and may be revised due to, potential access constraints, scheduled events, emergencies, or other unforeseen circumstances. Please keep checking this website for the latest information including any updates.
Current Buildings:
Current Buildings |
Status |
Wolfson Link |
In Progress |
Immediate Pipeline:
Next Building |
Status |
Fraser |
Due to commence in January 2025 |
Pearce Lodge |
Due to commence in January 2025
|
Maths Modular |
H1 2025 |
Florentine House |
H1 2025 |
James McCune Smith |
H1 2025 |
6 Lilybank Gardens |
H1 2025 |
8 Lilybank Gardens |
H1 2025 |
Hetherington House |
H1 2025 |
Accounts and Finance |
H1 2025 |
Sir Charles Wilson Building |
H1 2025 |
Future Pipeline (to March 2026):
Building |
---|